June 2022

Silo Camera Image

Riverside Offices Camera Image

Control Tower – Shuttering for Columns

Southern Roundabout – Drainage Trench

Waveney Drive – Footpath Broken Out

Pier 6 – Waterproofing

Pier 4 – Wet Plug Reinforced Cage for Concreting

Pier 4 – Safety Watch Diver

NAV 1 – Final Omnia Plank in Place
May 2022

Silo Camera – Late May 2022

Colin Law Way – Aerial View

Colin Law Way – Open for Use

NAV 1 – Omnia Planks installed

Control Tower – Mass Pour – Base

Pier 1 – UXO Probe Setup

Pier 6 – Installing Reinforcement Rebar

North Abutment – Shutters Removed – Wall E

Pier 7 – Stripping Shutters
April 2022

Colin Law Way – Finishing Touches

Basement Rebar – Control Tower

Pier 2 – Finished Concrete

Pier 7 – Shuttering Installed

Pier 6 – Temporary Works pre- excavation

North Abutment – Stripping Shuttering

Pier 5 – Working Platform

NAV 1 – Concrete Formwork Planks

Silo Camera View – Mid-April
March 2022

Northern Abutment Reinforce Bars

Arrival of NAV 1

Pier 7 – Base Backfill Complete

Control Tower – Threaded Wall Bars for Basement

Pier 5 Cofferdam – Pile Welding

Riverside Camera View – 23/3/22
February 2022

Image from Silo Camera – Early Feb

Pier 4 – Marine Piling Rig

Pier 7 – Pile Cropping

Pier 3 – Design Drawing as part of Control Tower

Pier 3 – Concrete Pour

Pier 3 – Removing Shuttering
January 2022

Essex & Suffolk Water Diversions
Rotterdam Road

King Post Installation
Waveney Drive

Retaining Wall – Lings
Riverside Road

Pier 4 Cofferdam and Walkway

Pier 2 and 3 – Backfilled Bases

Southern Approach – Aerial Work

Pier 3 Main Structure Rebar

Site Information Sign
Denmark Road

UK Power Network Sub-Station
Southern Landing Point
December 2021

Traffic Management
Rotterdam Road

Luffing Jib – Largest Crane on Site South Side

UK Power Network – Excavation
Waveney Drive

City Fibre – Duct Installation
Colin Law Way

First King Post Installation
Waveney Drive
November 2021

Drone Image of Colin Law Way

Earthworks
Colin Law Way

Pier 3 – First Concrete Pour
Aerial View

Pier 3 – Second Concrete Pour

Pier 4 & 5 Marine Works
Drone Image

Cofferdam Piling Gates
Pier 5

Councillor Matthew Hicks
BBC Look East Interview

Image from Silo Camera
Daytime

Image from Silo Camera
Early Evening
October 2021

Marine Works – Drone Image

Dewatering for Colin Law Way construction

Pier 2 Pilecap Excavation

Pier 4 Cofferdam Works

Pier 7 Pilecap Excavation

Pier 5 Cofferdam Works
September 2021

Marine Works – Dolphin Piles

Retaining Wall – Lings
Waveney Drive

Pier 3 Pile Caps

Pier 6 – Piling Cage Installation
North Side Quay

Manhole Base Installation
Colin Law Way

Image from Silo Camera
August 2021

Official Opening of Site Offices

Northern Abutment – CFA Piling

Earthworks and Drainage
Colin Law Way
July 2021

Site Information Sign
Waveney Drive

Traffic Management
Waveney Drive/Riverside Road

Claude Monique Crane Barge
Delivery to Gull Wing Site
June 2021

Pier 3 – Piling and Auger Rig

Entrance cleared for new
Colin Law Way

Anglian Water Sewer Diversions
Riverside Road

Dolphin Pile Manufacturing

Delivery of Dolphin Piles to quayside.

Pier 3 – Auger Drill
April/May 2021

Breaking up the Concrete
Northern Landing Point

Metal Shed Demolition –
Clearing for new Colin Law Way

Land Clearance
Colin Law Way

Suction Excavation Machine
used around the whole site.

Concrete Crusher
North Area Clearance

Pier 3 Footprint