November 2023

Including Site Drone Images

Hydraulic Pipes in SAV 4

Attenuation Tank - Southern Side

New Cycle and Pedestrian Pathway Under NAV 1

Visitor Open Day - Some of the Guests on the Bridge

Lake View of the Bridge

Rainbow over the site

October 2023

Silo Camera Image

Rolling Section Rack Construction

Control Tower - Inner Stairwell/Lift Shaft

Completed Control Tower External Walls

Pier 4 - Dolphin Pile Works

Hydraulic Pipes inside SAV 4

Northern Approach False Brickworks

New Roundabout Works - Northern Highway

New Footpath and Roadway - North Side

September 2023

Bascule Section construction at Westdorpe

Reinforced Edging Beams - Southern Approach

Edging Beams - Southern Approach

Maintenance Platform under SAV 1 l

Inside SAV 1

Control Tower - Inside Lower Room

Encapsulation Pour - Pier 4

Pier 5

New Road Network - Northern Approach

August 2023

Southern Approach Completed OmniaPlanks

SAV 4 - OmniaPlank Works

Concrete Pour - SAV 3

Bridge Deck - Reinforcement Bar Installation

Southern Approach Concrete Works

Control Tower - External Room Construction

Hydraulic Plant Installation

Northern Approach Work

Northern Approach Backfilling

July 2023

Fixed Camera Image

Riverside Road

Fixed Camera Image

Silo Camera

Electric Cable Trunking

Control Tower Plant Room

OmniaPlank Installation

Southern Approach

Reinforced Steel for Decking

Southern Approach

Northern Approach Embankment Exterior Walls

Drainage Works

Northern Road Network

New Northern Roundabout

Construction Works

Path and Road Edging

Northern Road Network

June 2023

Silo Camera - Late June 2023

Riverside Camera - Late June 2023

Aerial View of Southern Approach

Southern Approach - Tie-In Works

Southern Approach

Edge Beam Installation

Southern Approach

OminiaPlanks - SAV 3

Underneath Southern Approach with OmniaPlanks

Backup Generator

Control Tower Plant Room

Pier 4 - SAV End Piece

NAV 1 / Northern Approach

Northern Approach

Concrete Retaining Walls

Northern Roadworks /

Pavement Works

May 2023

Riverside Road Camera - Late May

Control Tower Core - External

Control Tower Core - View Looking Up Inside

Control Tower Core - Staircase

Southern Approach - Binding Pour

Northern Approach Retaining Wall

SAV 2&4 Arrival

SAV 3 Installation

SAV 4 Installation

Silo Camera Image Late May - (Shows all viaducts in place)

Southern Approach View

Concrete Omniplanks Ready for Installation on Steel Structures

April 2023

Silo Camera - Mid April

Riverside Road Camera - Mid April

Installation of NAV 3 over Lake

Installation of NAV 3 over Lake

Installation of NAV 3 over Lake

Pier 4

Control Tower Core

Southern Approach Embankment

Northern Approach Embankment

March 2023

View from Silo Camera - Early March

View from Riverside Road Camera - Early March

NAV 2 & 3 Lifting Crane

NAV 2 & 3 Arrival

Installing NAV 2

Installing NAV 3

Control Tower - Core Construction

Pier 4 Towers

Pier 5 - Complete

Southern Approach

Southern Approach

View from Control Tower

February 2023

Riverside Camera Image

Silo Camera Image

Lings - New Railings

Southern Approach - Wall Progress

Southern Approach - View from Abutment

Control Tower Core - Lift No. 5 Works

Southern Approach and Control Tower

Pier 4 - East and West Stems

Pier 5

January 2023

Riverside Camera Image

Silo Camera Image

Southern Approach Wall Construction

Southern Abutment Formwork Stripped

Control Tower - 2nd Lift

Control Tower - Plant Room Blockwork

Pier 4 - Tandem Concrete Pour

Pier 5 - Concrete Pour

Pier 5 - Concrete Pour Quayside View

December 2022

Riverside Road Camera Image

Silo Camera Image

Waveney Drive Fence Complete

Southern Roundabout Open

Southern Approach - Wall Construction Blocks First Layer

Pier 5 - Working Platform for 2nd Lift

November 2022

Riverside Camera Image

Silo Camera Image

Colin Law Way Opening

Waveney Drive - Fence Installation

Control Tower Sprinkler Tank

Southern Roundabout - Final Preparations

Southern Approach Footprint

South Abutment - Reinforced Bar Work

Pier 5 - Shuttering for Concrete Pour

October 2022

Riverside Camera Image

Silo Camera Image

Pier 1 - Breaking Down Piles

Control Tower - Sprinkler Tank Base Pour

Pier 4 - Piles Broken Down

Pier 5 - Installing Working Platform

Attenuation Tank 4 - Slab Pour Preparations

NAV 1 In Place

Southern Roundabout - Updated Image

September 2022

Silo Camera Image

Riverside Office Camera View

Southern Roundabout Works

Attenuation Tank 2 - Pre-Cast Walls

Riverside Road - Utilities Culverts

Control Tower - Continued Work

Pier 5 - Preparing Reinforced Bars for Concrete Pour to Base

Pier 4 - Welding Brackets for Strengthening Frame

Pier 6 - Backfilling Base

August 2022

Silo Camera Image

Riverside Offices Camera Image

Control Tower - Plant Room Roof Concrete Pour

NAV 1 - Parapet Installation

Pier 4 - Dewatered

Waveney Drive new path towards Southern Roundabout

July 2022

Silo Camera Image

Riverside Offices Camera Image

Canning Road - Compacting Base Layer on new Road

Southern Roundabout - Continued Work

Pier 4 - Wet Plug Concrete Pour

Pier 6 - Stem Reinforcement Bar

Pier 7 - Shuttering Stripped

NAV 1 - Deck Pour

Twin Town (Plasir - France) - Viewing site from site viewing deck

June 2022

Silo Camera Image

Riverside Offices Camera Image

Control Tower - Shuttering for Columns

Southern Roundabout - Drainage Trench

Waveney Drive - Footpath Broken Out

Pier 6 - Waterproofing

Pier 4 - Wet Plug Reinforced Cage for Concreting

Pier 4 - Safety Watch Diver

NAV 1 - Final Omnia Plank in Place

May 2022

Silo Camera - Late May 2022

Colin Law Way - Aerial View

Colin Law Way - Open for Use

NAV 1 - Omnia Planks installed

Control Tower - Mass Pour - Base

Pier 1 - UXO Probe Setup

Pier 6 - Installing Reinforcement Rebar

North Abutment - Shutters Removed - Wall E

Pier 7 - Stripping Shutters

April 2022

Colin Law Way - Finishing Touches

Basement Rebar – Control Tower

Pier 2 - Finished Concrete

Pier 7 - Shuttering Installed

Pier 6 - Temporary Works pre- excavation

North Abutment - Stripping Shuttering

Pier 5 - Working Platform

NAV 1 - Concrete Formwork Planks

Silo Camera View - Mid-April

March 2022

Northern Abutment Reinforce Bars

Arrival of NAV 1

Pier 7 - Base Backfill Complete

Control Tower - Threaded Wall Bars for Basement

Pier 5 Cofferdam - Pile Welding

Riverside Camera View - 23/3/22

February 2022

Image from Silo Camera - Early Feb

Pier 4 - Marine Piling Rig

Pier 7 - Pile Cropping

Pier 3 - Design Drawing as part of Control Tower

Pier 3 - Concrete Pour

Pier 3 - Removing Shuttering

January 2022

Essex & Suffolk Water Diversions

Rotterdam Road

King Post Installation

Waveney Drive

Retaining Wall - Lings

Riverside Road

Pier 4 Cofferdam and Walkway

Pier 2 and 3 - Backfilled Bases

Southern Approach - Aerial Work

Pier 3 Main Structure Rebar


Site Information Sign

Denmark Road

UK Power Network Sub-Station

Southern Landing Point

December 2021

Traffic Management

Rotterdam Road

Luffing Jib - Largest Crane on Site South Side

UK Power Network - Excavation

Waveney Drive

City Fibre - Duct Installation

Colin Law Way

First King Post Installation

Waveney Drive


November 2021

Drone Image of Colin Law Way

Earthworks

Colin Law Way

Pier 3 - First Concrete Pour

Aerial View


Pier 3 - Second Concrete Pour

Pier 4 & 5 Marine Works

Drone Image

Cofferdam Piling Gates

Pier 5


Councillor Matthew Hicks

BBC Look East Interview

Image from Silo Camera

Daytime

Image from Silo Camera

Early Evening


October 2021

Marine Works - Drone Image

Dewatering for Colin Law Way construction

Pier 2 Pilecap Excavation


Pier 4 Cofferdam Works

Pier 7 Pilecap Excavation

Pier 5 Cofferdam Works


September 2021

Marine Works - Dolphin Piles

Retaining Wall - Lings

Waveney Drive

Pier 3 Pile Caps

Pier 6 - Piling Cage Installation

North Side Quay

Manhole Base Installation

Colin Law Way

Image from Silo Camera


August 2021

Official Opening of Site Offices

Northern Abutment - CFA Piling

Earthworks and Drainage

Colin Law Way

July 2021

Site Information Sign

Waveney Drive

Traffic Management

Waveney Drive/Riverside Road

Claude Monique Crane Barge

Delivery to Gull Wing Site

June 2021

Pier 3 - Piling and Auger Rig

Entrance cleared for new

Colin Law Way

Anglian Water Sewer Diversions

Riverside Road

Dolphin Pile Manufacturing

Delivery of Dolphin Piles to quayside.

Pier 3 - Auger Drill

April/May 2021

Breaking up the Concrete

Northern Landing Point

Metal Shed Demolition -

Clearing for new Colin Law Way

Land Clearance

Colin Law Way

Suction Excavation Machine

used around the whole site.

Concrete Crusher

North Area Clearance

Pier 3 Footprint

Office access